CHERRY VALLEY — Progress is being made on two projects on the Cross County Schools campus.
One of those is the elementary school addition.
“It’s still slated to a mid- to late-March opening,” said Cross County Superintendent Dr. Nathan Morris. “We were behind a little bit, as we’ve said during the summer, on dirt work. We had to undercut a little more, maybe, than we thought we would.
“This past week was a little bit slow. The last couple weeks they were doing the block for the safe room. That mortar had to have a certain compaction test. After seven days, it didn’t meet it, so they couldn’t continue on with the steel beams around it and then test it again at 14,” Morris added. “At 14, it passed compaction, so then they could go through with the steel. If it wouldn’t have passed at 14, they were going to have to reinforce.
“It’s a FEMA-rated safe room. That took a little bit of time to get it right, or make sure it was going to be right, and it is,” he continued. “Now, erection of steel will take place, and once we go vertical on the building, most of the building is prefabricated, it’s sitting out on the west side of the football field, so things will progress pretty handily on the elementary project now.”
The other one is the high school gym project.
“It looks like we still start lightweight concrete sometime between Friday and Monday of next week. That takes about three days to cure and dry over the panels on top of the gym roof,” Morris said. “The insulation and roofing will be about a two-day project. They’ll do half in one day, half in the other. We think we’re going to beat the Nov. 2 timeline for the roof. That’s just the roof, though.
“That’s not getting back in it because we still have electricity and we have painting and we have cleanup and we have a gym floor to put back down to refinish,” he added. “We have our gym floor contractors ready on two dates — Nov. 16 and Nov. 30.”