CROSS COUNTY — Construction projects are underway for both the Wynne and Cross County School Districts.
The major one is the new Wynne High School.
“Probably our biggest need right now is they’re ready to start putting the glass in on the two wings,” said Wynne Superintendent Dr. Kenneth Moore. “Obviously the south wing is not completely ready but they’re getting close. As they get that glass in here in the next three to four weeks, that building’s going to be 95% in the dry. As they finish the roof on that south side, it will be in the dry. That’s the big, big piece right now heading into winter.”
Moore said while the drought has hurt farmers, it has helped in the construction progress for the new high school.
“The lack of rain has really helped us at that building. They’re still on target, actually gained some days because of the no rain,” he said. “It’s looking good inside that north side. They are sheet rocking, mudding. They already have started painting on that side. They started painting the rails that are up on the second floor and on the stairwells. That’s another big huge milestone once the paint starts, you know you’re headed towards finishing.”
Moore said the goal is to begin the 2027-28 school year in the new Wynne High School.
The goal is much sooner than that for the elementary school addition at Cross County.
“It’s still slated to a mid- to late-March opening,” said Cross County Superintendent Dr. Nathan Morris. “We were behind a little bit, as we’ve said during the summer, on dirt work. We had to undercut a little more, maybe, than we thought we would.
“The last couple weeks they were doing the block for the safe room. That mortar had to have a certain compaction test. After seven days, it didn’t meet it, so they couldn’t continue on with the steel beams around it and then test it again at 14,” he added. “At 14, it passed compaction, so then they could go through with the steel. If it wouldn’t have passed at 14, they were going to have to reinforce.
“It’s a FEMA-rated safe room. That took a little bit of time to get it right, or make sure it was going to be right, and it is,” Morris continued. “Now, erection of steel will take place, and once we go vertical on the building, most of the building is prefabricated, it’s sitting out on the west side of the football field, so things will progress pretty handily on the elementary project now.”
Another project is the repair of the roof at the high school gym. Morris said lightweight concrete work will be completed soon.
“That takes about three days to cure and dry over the panels on top of the gym roof,” he said. “The insulation and roofing will be about a two-day project. They’ll do half in one day, half in the other. We think we’re going to beat the Nov. 2 timeline for the roof. That’s just the roof, though.
“That’s not getting back in it because we still have electricity and we have painting and we have cleanup and we have a gym floor to put back down to refinish,” Morris added. “We have our gym floor contractors ready on two dates — Nov. 16 and Nov. 30.”
The Cross County High School gym was damaged by straight-line winds earlier this year, while Wynne High School was one of hundreds of buildings and homes destroyed or damaged in the March 31, 2023, tornado.